Location: Berrybank, 80km west of Geelong, 14km east of Lismore
Technology: V136 – 4.2MW Vestas wind turbines
Number of turbines: 26 Wind Turbines (Stage 2) and joining 43 Wind Turbines (Stage 1)
Total installed capacity: 180.6 MW (Stage 1) and 109.2MW (Stage 2)
Turbines blade tip height: 180 meters
Connection: To the Grid via the 220kV Ballarat-Terang Transmission Line

Berrybank 2 Wind Farm Sustainability

Sustainability

We are fully aware that, in order to create value and build trust, we need to combine our corporate responsibility with stakeholders with the utmost level of sustainability and long-term thinking.

Mindful of the importance that our actions have for the people and environment where we operate, we establish a series of commitments that guarantee wellbeing (current and future) for the people and environments we come into contact with.

Berrybank 2 Wind Farm News

News

Find below the latest news and information (fact sheets, media releases, local community outlets, external news articles) about the project.

Berrybank 2 Wind Farm About

About the project

GPG Australia has also developed the Berrybank 2 Wind Farm, which is an approved 26 turbine wind farm located on an area covering about 5,000 hectares within the Victorian district known as the Western Plains, located with the Corangamite and Golden Plains Local Government Areas.

Berrybank 2 Wind Farm

Our company

Global Power Generation Australia (GPGA) is the Australian subsidiary of Global Power Generation (GPG), the international generation arm of Naturgy Group (Naturgy). GPG was created in 2014, in order to bring together the international power generation assets and business for the company outside Europe, with the participation of the Kuwait Investment Authority (KIA).

In the spirit of reconciliation, GPG acknowledges the Traditional Custodians of country throughout Australia and their connections to land, sea and community. We pay our respect to their Elders past and present and extend that respect to all Aboriginal and Torres Strait Islander peoples today.

The Berrybank wind farm is located on the lands of the Wathaurong and Eastern Maar people and we wish to acknowledge them as Traditional Owners.

The project

Progress

You might also be interested in

Community

Detailed information about the Community Engagement and Benefit Sharing Plan associated to the project during the Construction and Operation phases can be found here 

Relevant documentation

Get access to endorsements and permitting documentation for all key aspects of the project from compliance, modifications and all plans for key assessments.